Meeting Time: July 21, 2020 at 6:00pm PDT
The online Comment window has expired

Agenda Item

10. 20-0241 Consider: 1) Appropriating $41,250 from the Water Fund Balance to the Block 35 Elevated Tank Painting Project; 2) Awarding a Construction Contract to Unified Field Services Corporation for the Block 35 Elevated Tank Painting Project for $1,411,389; 3) Authorizing the City Manager to Approve Additional Work if Necessary, for up to $70,582; 4) Approving the Plans and Specifications for the Project; 5) Approving the Design, Layout, and Installation of the City Name and Logo on the Elevated Tank; and 6) Awarding an Inspection Services Agreement with Coating Specialists and Inspection Services, Inc. for the Block 35 Elevated Tank Painting Project for $158,840 (Public Works Director Katsouleas). ADOPT RESOLUTION NOS. 20-0087 AND 20-0088