Agenda Item

12. 21-0269 Consideration of the Following for Cycle 1 Water Infrastructure Improvement Project: a) A Resolution Awarding a Construction Agreement to Stephen Doreck Equipment Rentals, Inc. for the Cycle 1 Water Infrastructure Improvement Project for $2,210,484.30; Approving the Plans and Specifications for the Project; and Authorizing the City Manager to Approve Additional Work, if Necessary, for up to $221,048;and b) A Resolution Approving an Inspection Services Agreement with Onward Engineering, Inc. in the Amount of $204,930 (Public Works Director Lee). ADOPT RESOLUTION NOS. 21-0085 AND 21-0086